THE ASSIGNMENT
Connection of new tracks and turnouts in connection with the establishment of new NISB tracks at Høje Taastrup Station. The project required the cutover and commissioning of the modified DSB 1972 type interlocking. Execution took place on 7–8 April 2025.

VALUE DELIVERED
The project was delivered efficiently and on schedule. The cutover and subsequent testing were completed without deviation, and the installation was placed in service correctly and safely.

MY ROLE
Cutover and testing manager, responsible for executing the cutover, for the testing and commissioning of the modified interlocking, and for its entry into service, including fault-finding.